Short fim Gantt chart
Short Film Gantt Chart | ||||||||||||||
Task | Milestones | Contingency | Resources and Personnel | 10th May | 17th May | 24th May | 31st May | 7th June | 14th June | 21st June | 28th June | 5th July | 12th July | 19th July |
Source Location | Might need multiple locations | |||||||||||||
Location Recce | Might need multiple locations | |||||||||||||
Get Location permission forms signed | Locations might fall through, or you might need multiple locations | |||||||||||||
Casting director to host auditions | There might have to be another/multiple days of auditions | |||||||||||||
Mind map ideas for short film | ||||||||||||||
Get script writer to write the script | ||||||||||||||
Second draft script | ||||||||||||||
Send script to client | Client might not like the script - 3rd draft | |||||||||||||
Shot by shot list | ||||||||||||||
Draw a storyboard | Storyboard might take a bit longer than anticipated | |||||||||||||
Source equipment (camera, tripods etc) | Equipment might already be booked - can only get at a later date | |||||||||||||
Get actor permission forms signed | ||||||||||||||
Mood-board costumes for actors | ||||||||||||||
Size up actors for costumes | ||||||||||||||
Hire caterers | ||||||||||||||
Write call sheets | ||||||||||||||
Asset table | ||||||||||||||
Get makeup artists for the actors | ||||||||||||||
Make sure sets and props are ready | ||||||||||||||
Budget for promotion and advertising | ||||||||||||||